Bundle contractor jobs: EV breaker, Tesla Wall Connector, front outlet, A/C switch, and circulator removal

Closed
#1,942 0 comments 0 reactions 0 assignees View on GitHub
House Research
Dominant language
Python
Stars
5.3k
Forks
500
PR merge metrics
No merged PRs in 30d

Description

## Goal

Bundle these five electrical/plumbing jobs into one coordinated contractor visit. Confirm in advance whether a plumber is required for the water-side circulator work.

## Work items

- [ ] **EV breaker:** Diagnose and replace the stuck/failed 30A two-pole breaker. Inspect the panel connection, bus, existing EV-circuit conductors, and terminations for heat or damage before reusing the circuit.
- [ ] **Tesla Wall Connector:** If the existing circuit passes inspection, remove the current 240V EV receptacle and hardwire the Tesla Wall Connector using the existing circuit. Commission it for a **30A circuit / 24A maximum continuous charge**.
- [ ] **Front outside outlet:** Complete the work tracked in #1513, including resolving the rain-related tripping problem and replacing the affected outdoor receptacle/equipment as appropriate.
- [ ] **A/C safety trip switch:** Complete the installation tracked in #838 and verify that the safety switch operates correctly.
- [ ] **Water-heater circulator:** Safely disconnect and remove the unwanted circulator near the water heater and leave any electrical wiring safely terminated or removed. This supersedes the automation idea tracked in #100.

## Completion checks

- [ ] Electrician confirms the EV circuit wiring and panel connection are safe for continued use.
- [ ] Tesla Wall Connector is permanently limited to 24A and completes a charging test without abnormal heat or breaker behavior.
- [ ] Front outlet is weather-protected and passes a functional/GFCI test.
- [ ] A/C safety switch is tested after installation.
- [ ] Circulator is removed, its electrical feed is safely handled, and the capped plumbing remains leak-free after water service is restored.
- [ ] Add final notes/photos to this issue and close #1513, #838, and #100 when their work is complete.

Contributor guide

No contributing guide indexed for this repository

Research direction

No repository files, tests, or code entry points are mentioned. Review the five work items and completion checks, then consult the related issues #1513, #838, and #100; done means the contractor completes and verifies each electrical/plumbing job and records final notes or photos.

Written by the indexing model from the issue text.

Assessment

Domain
infrastructure
Issue type
Feature
Difficulty
5/5
Estimated time
Over a week
Activity status
Active
Clarity
Clearly specified
Newbie friendliness
10/100